Engineering case study

Dewatering stabilised after recurring pump station failures

Repeat pumping failures threatened the water balance of an operating mine. A structured audit rebuilt both the system and the reporting around it.

Commodity
Diamond
Location
South Africa
Duration
7 weeks

The challenge

Recurring pump failures compromised dewatering capacity, with rising energy cost per cubic metre and no reliable water balance visibility.

Our approach

  1. 01

    System audit

    Pump station-by-station audit of duty points, wear, control philosophy and standby capacity.

  2. 02

    Water balance model

    Inflow, storage and pumping capacity modelled to expose the true constraint.

  3. 03

    Selection correction

    Pump and impeller selection corrected to duty, with revised maintenance intervals.

  4. 04

    Reporting framework

    MHSA-aligned reporting framework so water risk stays visible to management.

Outcomes

  • Water balance stabilised
  • Audit closure achieved
  • Energy per cubic metre reduced through correct duty-point selection

More engineering case studies

  • Platinum & Gold — Scraper winch failures resolved and Section 54 instruction upliftedPlatinum & Gold

    Scraper winch failures resolved and Section 54 instruction uplifted

    Repeat scraper winch failures were stopping production and exposing crews to rope and entanglement risk. We ran an independent investigation and closed the instruction out.

    Upliftment success
    100%

    Upliftment success

    Repeat failures post close-out
    0

    Repeat failures post close-out

    Investigation to closure
    6 wks

    Investigation to closure

    Read case study
  • Manganese — Shaft signalling redesigned to restore compliant hoisting availabilityManganese

    Shaft signalling redesigned to restore compliant hoisting availability

    Signalling failures on a hoisting installation were halting vertical transport. We rebuilt the signalling protocol and the compliance evidence behind it.

    Signalling compliance
    100%

    Signalling compliance

    Assessment to commissioning
    10 wks

    Assessment to commissioning

    Hoisting availability restored
    24/7

    Hoisting availability restored

    Read case study

Let's solve the engineering problem in front of you.

Whether it's a regulator instruction, a failing asset or a capital project, we start with an honest engineering assessment.