All case studies

Engineering case study

Conveyor fire risk closed out after a regulator finding

A regulator flagged conveyor fire hazards across a coal handling plant. We built the risk matrix, the preventive regime and the standards uplift that closed it.

Commodity
Coal
Location
Mpumalanga, South Africa
Duration
8 weeks

The challenge

Belt misalignment, idler seizure and material spillage created a credible fire risk across a long overland and plant conveyor network.

Our approach

  1. 01

    Hazard mapping

    Every drive, transfer point and idler run assessed and scored in a fire risk matrix.

  2. 02

    Preventive regime

    Inspection frequencies, tracking standards and cleaning routines built into the maintenance plan.

  3. 03

    Standards uplift

    Guarding, hot-work and fire detection standards revised and rolled out to crews.

  4. 04

    Verification

    Post-implementation audit evidencing sustained compliance to the regulator.

Outcomes

  • DMPR instruction uplifted
  • Fire risk rating reduced across all transfer points
  • Belt life extended through corrected tracking and tension

More engineering case studies

  • Platinum & Gold — Scraper winch failures resolved and Section 54 instruction upliftedPlatinum & gold mining

    Project Winch Guard

    Scraper winch failures resolved and Section 54 instruction uplifted

    Platinum & Gold · North West, South Africa · 6 weeks

    Repeat scraper winch failures were stopping production and exposing crews to rope and entanglement risk. We ran an independent investigation and closed the instruction out.

    • Incident investigation
    • Mechanical engineering
    • MHSA compliance
    Upliftment success
    100%

    Upliftment success

    Repeat failures post close-out
    0

    Repeat failures post close-out

    Investigation to closure
    6 wks

    Investigation to closure

    Read case study
  • Manganese — Shaft signalling redesigned to restore compliant hoisting availabilityManganese mining

    Project Shaft Signal

    Shaft signalling redesigned to restore compliant hoisting availability

    Manganese · Northern Cape, South Africa · 10 weeks

    Signalling failures on a hoisting installation were halting vertical transport. We rebuilt the signalling protocol and the compliance evidence behind it.

    • Shaft & winding plants
    • Compliance engineering
    • EPCM
    Signalling compliance
    100%

    Signalling compliance

    Assessment to commissioning
    10 wks

    Assessment to commissioning

    Hoisting availability restored
    24/7

    Hoisting availability restored

    Read case study

Let's solve the engineering problem in front of you.

Whether it's a regulator instruction, a failing asset or a capital project, we start with an honest engineering assessment.