Engineering case study

Conveyor fire risk closed out after a regulator finding

A regulator flagged conveyor fire hazards across a coal handling plant. We built the risk matrix, the preventive regime and the standards uplift that closed it.

Commodity
Coal
Location
Mpumalanga, South Africa
Duration
8 weeks

The challenge

Belt misalignment, idler seizure and material spillage created a credible fire risk across a long overland and plant conveyor network.

Our approach

  1. 01

    Hazard mapping

    Every drive, transfer point and idler run assessed and scored in a fire risk matrix.

  2. 02

    Preventive regime

    Inspection frequencies, tracking standards and cleaning routines built into the maintenance plan.

  3. 03

    Standards uplift

    Guarding, hot-work and fire detection standards revised and rolled out to crews.

  4. 04

    Verification

    Post-implementation audit evidencing sustained compliance to the regulator.

Outcomes

  • DMPR instruction uplifted
  • Fire risk rating reduced across all transfer points
  • Belt life extended through corrected tracking and tension

More engineering case studies

  • Platinum & Gold — Scraper winch failures resolved and Section 54 instruction upliftedPlatinum & Gold

    Scraper winch failures resolved and Section 54 instruction uplifted

    Repeat scraper winch failures were stopping production and exposing crews to rope and entanglement risk. We ran an independent investigation and closed the instruction out.

    Upliftment success
    100%

    Upliftment success

    Repeat failures post close-out
    0

    Repeat failures post close-out

    Investigation to closure
    6 wks

    Investigation to closure

    Read case study
  • Manganese — Shaft signalling redesigned to restore compliant hoisting availabilityManganese

    Shaft signalling redesigned to restore compliant hoisting availability

    Signalling failures on a hoisting installation were halting vertical transport. We rebuilt the signalling protocol and the compliance evidence behind it.

    Signalling compliance
    100%

    Signalling compliance

    Assessment to commissioning
    10 wks

    Assessment to commissioning

    Hoisting availability restored
    24/7

    Hoisting availability restored

    Read case study

Let's solve the engineering problem in front of you.

Whether it's a regulator instruction, a failing asset or a capital project, we start with an honest engineering assessment.